Location | Whitford Road, Bromsgrove |
Value Circa | £700,000.00 |
Duration | Contract started Nov 2022 – Jan 2023, 3 Month Duration |
Scope | Bulk Earthworks |
Description | Topsoil strip depth 350mm placed to a temporary on-site stockpile, excavate to reduce levels within cut profile, fill to formation. Modification of site-won materials to achieve specification requirements for fill materials. Site won topsoil filled to pond. SGE’s scope also included place only imported granular material and load only disposal off-site of all surplus topsoil and muck materials. |
Key Matters | Inherit material suitability, surface water run-off, mass haul management, environmental issues, programme constraints, client critical path management. |
Reference | Available on request from Ross Heron; 07811 835858 |
Contact | Ross Heron, Commercial Manager; 07811 835858 |