Location | Swindon TNT Distribution |
Value circa | £525,000 |
Duration | Contract started January 2015, 8 week duration |
Scope | Vegetation strip Bulk excavation cut to fill Soil modification and Stabilisation Supply, place and compact Type 1 Sub base |
Description | Distribution Centre |
Key issues | Detailed sequence of works for sectional handover of building (2 Phases) Dealing with unsuitable compressive soils beneath structures Value engineered stabilised piling platform Value engineered levels omitting off site disposal Utilising on site “borrow pit” |
References | Available on Request from Eddie Ronald: 07714 287 108 |
Contact | Eddie Ronald, Operations Director 07714 287 108 |