Location | Plot 15, Southend (CAMA) |
Value Circa | £ 90,000 |
Duration | Contract started May 2023 & finished May 2023, 3 Week Duration |
Scope | Bulk Earthworks |
Description | Topsoil strip depth 200mm, excavate to reduce levels within cut profile, excavate to reduce levels within attenuation tank, fill to formation & place imported geotextile material. SGE’s scope also included place only imported granular material, supply and load road wagons with site-won surplus fill material & load only disposal off-site of all surplus topsoil materials. |
Key Matters | Inherit material suitability, surface water run-off, mass haul management, environmental issues, programme constraints, client critical path management. |