| Location | Mickle Well Park, Daventry |
| Value circa | £1,915,000 |
| Duration | Contract started July 2019 – 27-week programme over one visit |
| Scope | Site clearance, supply & install permanent site fencing, hard breakout of existing road, bulk earthworks, soil modification, supply and installation of farmers access road and 2nr. reinforced service protection slabs. |
| Description | Installation of bulk earthworks for a circa 190,000m2 housing development situated in Daventry. |
| Key issues | Principle Contractor responsibilities, works programme and sequence, existing underground & overhead services, material supply (Type 1 & concrete) and hard excavation of natural materials. |
| References | Available on request from Brian Heron: 07841 341240 |
| Contact | Brian Heron, Managing Director: 07841 341240. |