| Location | London Medway, Kent |
| Value circa | £300,000 |
| Duration | Contract started February 2020 – 7-week programme over one visit. |
| Scope | The construction of a distribution unit with car and HGV park. |
| Description | Cut to fill and modification of site won material, stabilise to 30% CBR final layer and import and place type 1 subbase to produce piling mat in the building and the externals. |
| Key issues | Environmental restrictions, tight programme constraints, difficult ground conditions. |