| Location | Tadpole Farm, Swindon |
| Client | Breheny |
| Value circa | £150,000 |
| Duration | April / May 2014, 4 Week programme, works will be completed on time. |
| Scope | 10,000m3 topsoil strip 25,000m3 of Earthworks cut to fill 5,000m3 re-soil |
| Description | The project was for development of a housing scheme for Breheny. |
| Key issues | • Restricted programme and sequencing the works. • Environmentally sensitive surroundings |