| Location | Didcot Power Station, Bulk Earthworks & Soil Stabilisation Erith Contractors |
| Value Circa | £628,132.50 |
| Duration | Contract started November 2019 – December 2019, 7 Weeks Duration |
| Scope | Bulk Earthworks & Soil Modification |
| Description | Fill of Power Station |
| Key Matters | Footprint Inherit materials suitability, working alongside othertrades in close proximity. |
| Reference | Available on request from Ross Heron; 07811 835858 |
| Contact | Ross Heron, Senior Quantity Surveyor; 07811 835858 |