Location | Alloa, Midtown Phase 2 – BHC Ltd |
Value Circa | £ 1,700,000 |
Duration | Contract started Sept – Oct 2022 & Mar – May 2023, 4 Month Duration |
Scope | Bulk Earthworks & Soil Stabilisation |
Description | Installation of temporary earthworks open grips, Topsoil strip depth 75mm, excavate to reduce levels within cut profile, fill to formation & fill surplus material to temporary stockpile. Soil stabilisation of underside of fill, base of excavation and all fill layers within the hard landscaping. SGE’s scope also included place only imported granular material and load only disposal off-site of all surplus topsoil materials. |
Key Matters | Inherit material suitability, surface water run-off, mass haul management, environmental issues, programme constraints, client critical path management. |