| Location | Dartford |
| Value Circa |
£420,000.00 |
| Duration | Contract started April – June. 2026, 10 Week Duration |
| Scope | Bulk Earthworks & Soil Modification |
| Description | Backfill and form existing ditch, over excavate peat material below earthworks profile, excavate to reduce levels within cut profile, excavate attenuation tank, fill to formation, soil modification, soil stabilisation within hard landscape, place site won granular depth 100mm, SGE’s scope also included load only of surplus materials from site. |
| Key Matters |
Inherit material suitability, mass haul management, programme constraints, client critical path management |
| Reference | Available on request from Ross Heron; 07811 835858 |
| Contact | Ross Heron, Commercial Manager; 07811 835858 |