Location: Needham Chalk Pit, Suffolk
Value: Circa £2,200,000
Duration: Contract started June 2016 – 43 week programme, two visit
Scope: Site clearance, bulk earthworks, soil modification, soil stabilisation, vertical band drains, placing drainage blanket, surcharging of fill, settlement monitoring, placing 6A as existing lake backfill and placing type 1 sub base
Description: Construction of housing development plateaus in a disused chalk pit
Key Issues: Works programme and sequence, ecology, value engineering with site won materials, bad drain installation and weather