Location Leybourne Chase Primary School, West Malling Kent
Value Circa £105,000
Duration Contract started Mid March 2015, 4 week duration
Scope Bulk excavation circa 10,000 m3, 5% CBR soil modification,Placing granular materials
Description Earthworks and stabilisation of site won wet materials and granular materials placement
Key Issues Programme, weather, adjacent properties