| Location | Stafford |
| Value Circa |
£176,000.00 |
| Duration | Contract started March – May. 2026, 7 Week Duration |
| Scope | Bulk Earthworks |
| Description | Topsoil strip depth 300mm, excavate to reduce levels within cut profile, fill to formation. SGE’s scope also included excavation of peat material and forming in a temporary stockpile. |
| Key Matters |
Inherit material suitability, mass haul management, programme constraints, client critical path management |
| Reference | Available on request from Ross Heron; 07811 835858 |
| Contact | Ross Heron, Commercial Manager; 07811 835858 |