Location | Tilbury Distribution Centre |
Value circa | £300,000 |
Duration | Contract started late October 2014, 8 week duration |
Scope | Bulk excavation, cut to fill Soil modification and stabilisation Place compact and trim granular materials |
Description | Distribution Centre |
Key issues | Detailed work sequence for sectional handover of the building platform Value engineered solution using soil stabilisation to avoid unsuitable material within the building footprint and produce a piling mat |